Here is a summary of each Phase of our development and how much it will cost.

The overall project budget is €580k, with €355k covering completion of Phase 1.

At present we are focusing entirely on Phase 1 and getting that completed and paid for.
Phases 2 and 3 will follow as soon as possible, but subject to funding.

In order for us to complete Phase 1 we have acquired a Credit Union Loan for amount of €150k. 
The loan repayments on this commence in October 2105 over 20 years.

HOWEVER, in order for us to not leave a financial debt on future generations, and more importantly, in order to complete Phases 2 and 3, it will be out intention to fundraise over the coming period in order to reduce our debt.

The sooner this loan is cleared, then the sooner we can commence Phases 2 and 3.

THEREFORE, INITIAL FUNDRAISING TARGET IS €150,000

DEVELOPMENT COSTS
1. Site purchase, enabling Works €85,000
2. Phase 1 including Pitch Development , Boundary Wall , Treatment Plant, Walkway)– €270,000
3. Phase 2 including Floodlighting €150,000
4. Phase 3 including Astro Turf Pitch  , final landscaping — €75,000
Total €580,000